2024 Street & Alley Paving Schedule

2024 Street & Alley Paving Schedule

City crews and contractors will soon begin the annual street & alley paving project. This includes repairs to curbs, gutters, and storm drains, new pedestrian ramps at intersections, and mill & overlay paving. During these projects, detours and/or altered parking may occur. Please see the attached map and list of streets & alleys that will be affected. Dates are tentative and subject to change.

April 29th - May 24th
  • Green Acres Dr., Calla Ct., and Iris Ct.
  • La Mar Dr. (West & East) and La Mar Ct.
  • Castle Dr. and Patricia Ct.
June 3rd - June 13th
  • Lyndale St. & Stewart St. Alley
  • Wall St. & Lyndale St. Alley
  • Range St. & Wall St. Alley
Thank you for your cooperation and patience during these improvements. Questions may be directed to the Public Works Department at 507-345-5570.